Avatara Condominium Mae Phim
02 二月 2011 Building A:
Tiling works in floors 2,3,4,5,6 complete, 7 floor nearly complete
Aluminum door installation ongoing
Block works and plastering in shop house units and ground floor area
Plastering works on roof including swimming pool
Block works at fire stairs
Outside plastering ongoing
Electrical and sanitary piping follows block works
Building B:
Pile cap foundation completed
Ground floor beams work has started