17 十二月 2010 New Nordic VIP 1, development site Dear buyer of apartment in “New Nordic VIP-1 Condominium”, and other interested:
•
• CONSTRUCTION HISTORY:
• · Our new condominium “VIP-1” was piled in May 2010.
• · From June 2010 to October 2010 we constructed the whole building in just 5 months to be “on roof”.
• · In October 2010 and November 2010 we constructed all interior and exterior walls, electric system, plumbing, water tanks etc.
• · Now in December 2010 we have been waiting for the roof tiles, and we have meanwhile done “small work” inside.
•
• STATUS NOW:
• · Two weeks ago brown roof tiles was to be delivered us by a mistake, of course we changes this to get the correct black (as prospect), and these will now come in short time.
• · We have made a fence against the street to protect the constructing area from the public road.
• · 4-8 persons work with after work in interior and exterior walls, when we still wait for the roof.
•
• FURTHER PROGRESS:
• · The black roof tiles will come soon, and to be completed.
• · When the roof is complete with tiles we can start all the “inn door work” that require roof to nor get ruined by water
• · We will make double exterior walls
•
• In our area and in Thailand in general it is many finished complexes. The developer usually use “single Q-block” bricks in the walls in these projects (this includes the earlier Nordic complexes). Now it is a new model called “K-block” that is better to protect the heat, more water resistant and more sound proof. We have chosen this new “K-block” ..... >>>>>
|